30TH MARCH 2020


Construction carries on…


Fonte Algarve Residences are strictly following government guidelines regarding the CoronaVirus and we are thankful that construction is allowed to continue. We are doing everything possible to be responsible and safe.
Construction progress update:

Installations (Electrical, Hydraulics and Air Conditioning)

Pipework to finish week ending 05/04/2020 on properties A11, A13, A12 and A14 with A05 already finished. This will enable us to move onto the next phase of construction as these properties are really taking shape.



Civil Construction

Giving support for the installations.

Preparing works for the plastering team (inside the villas), that will start week commencing 06/04/2020 on A05, and after A11 and A13.

Preparation of the swimming pools for the Holland AquaSight Acrylic Pool windows (www.hollandaquasight.com/en/) on properties A05, A11, A13, A14 and A12. Very exciting to see the first of these windows being installed.

Stay Safe and Stay Healthy