3RD APRIL 2020


Here’s what we have planned for
next month (May 2020)…


The plan for the month of May will consist of the following:

- Internal Wall plastering on villas A05, A11, A13;

- Finish pipe installations in 4 other villas;

- Aluminium windows and doors installation in A05, and start fabrication
on 7 more villas (A11, A12, A13, A14, A10, A08 and A07);

- Swimming pool impermeabilization on 4 villas ;

- External plaster on the facades (A11, A13, A12, A14);

- Begin the finishes on A05 (ceramic tiles on floor).

Obviously the the above works are dependent on the conditions presented during April. Everyone at Fonte Algarve Residences are taking all precautions very seriously and we are adhering to all guidelines. We will continue to adapt as the government will continue to react to the threat of the virus and may introduce new measures.

Stay Safe and Stay Healthy




3RD APRIL 2020

Here’s what we have planned for
next month (May 2020)…

The plan for the month of May will consist of the following:

- Internal Wall plastering on villas A05, A11, A13;

- Finish pipe installations in 4 other villas;

- Aluminium windows and doors installation in A05, and start fabrication on 7 more villas (A11, A12, A13, A14, A10, A08 and A07);

- Swimming pool impermeabilization on 4 villas ;

- External plaster on the facades (A11, A13, A12, A14);

- Begin the finishes on A05 (ceramic tiles on floor).

Obviously the the above works are dependent on the conditions presented during April. Everyone at Fonte Algarve Residences are taking all precautions very seriously and we are adhering to all guidelines. We will continue to adapt as the government will continue to react to the threat of the virus and may introduce new measures.